Here in full is the list of building work that will be needed to help turn Bradford's three-tier education system into a two-tier one.

PRIMARY SCHOOLS

Addingham alterations to Addingham Middle School will take nine months; Aire View Infant alterations to existing site will take nine months; All Saints CE (Bradford) alterations to existing site will take 12 months; All Saints CE (Ilk) new school at Skipton Road site will take 27 months; Allerton alterations to existing site will take 9 months; Ashlands extensions and alterations to existing site will take 21 months; Atlas alterations to existing site will take 9 months.

Baildon CE VA alterations to Ladderbanks Middle School site will take 18 months; Bankfoot alterations to existing site will take 9 months; Barkerend alterations to existing site will take 9 months; Blakehill extensions and alterations to existing site will take 27 months; Bolling Road alterations to existing site will take 18 months; Bowling Park alterations to Ryan Middle School site will take 9 months; Brackenhill alterations to existing site will take 9 months; Bradford Moor alterations and extensions to existing site will take 9 months; Burley alterations to Burley Middle site will take 9 months; Burley Woodhead CE alterations to existing site will take 18 months; Buttershaw alterations to existing site will take 18 months; Byron New School on Myra Shay will take 30 months;

Cavendish alterations to existing site will take 18 months; Clayton CE alterations and extensions to existing site will take 24 months; Cooper Lane alterations to existing site will take 18 months; Copthorne extensions to existing site will take 24 months; Cottingley alterations to Stoney Lee Middle School site will take 9 months; Crossflatts alterations to Ryshworth Middle School site will take 9 months; Crossley Hall alterations to existing site will take 18 months; Cullingworth alterations and extensions to existing site will take 21 months;

Denholme alterations and extensions to existing site will take 21 months; Drummond alterations to existing site will take 9 months;

East Morton CE alterations and extensions to existing site will take 18 months; Eastburn Junior and Infants alterations to existing site will take 21 months; Eastwood alterations and extensions to existing site will take 21 months; Eccleshill alterations and extensions to existing site will take 18 months; Eldwick alterations to Gilstead Middle School site will take 18 months;

Fagley extensions and alterations to existing site will take 18 months; Farnham alterations to existing site will take 9 months; Ferniehurst alterations to existing site will take 9 months; Feversham alterations and extensions to existing site will take 18 months; Foxhill GM alterations and extensions to existing site will take 18 months; Frizinghall alterations to existing site will take 18 months;

Girlington alterations and extensions to existing site will take 18 months; Glenaire alterations and extensions to existing site will take 18 months; Grange Road alterations to existing site will take 18 months; Green Lane alterations to existing site will take 9 months; Gregory alterations to existing site will take 9 months; Grove House alterations and extensions to existing site will take 24 months; Guard House alterations to existing and Calversyke Middle sites will take 24 months;

Harden alterations and extensions to existing site will take 18 months; Haworth alterations to Hartington Middle School site will take 9 months; Heather Grove alterations to Heaton Middle School site will take 9 months; High Crags alterations and extensions to existing site will take 24 months; High Fernley alterations and extensions to existing site will take 18 months; Hill Top CE GM alterations to existing site will take 9 months; Hollingwood GM alterations and extensions to existing site will take 24 months; Holme alterations to existing site will take 9 months; Holmefield alterations to existing site will take 12 months; Holy Trinity CE extensions and alterations to existing site 18 months; Holycroft new school will take 30 months; Horton Bank Top alterations to Mandale Middle School site will take 9 months; Horton Park alterations to existing site will take 9 months; Hothfield Street Junior alterations to existing site will take 18 months; Hoyle Court alterations and extensions to existing site will take 18 months;

Idle CE extensions and alterations to existing site will take 12 months; Ingrow alterations to existing site will take 9 months;

Killinghall GM alterations and extensions to existing site will take 18 months;

Larchmont alterations and extensions to existing site will take 18 months; Laycock alterations and extensions to existing site will take 18 months; Lees alterations and extensions to existing site will take 18 months; Ley Top alterations and extensions to existing site will take 9 months. Lidget Green extensions and alterations to existing site will take 24 months; Lilycroft alterations to existing site will take 9 months; Long Lee alterations to Swire Smith Middle School site will take 9 months; Low Ash extensions and alterations to existing site will take 27 months; Lower Fields alterations to existing site will take 9 months; Low Moor CE extensions and alterations to existing site will take 21 months;

Margaret McMillan alterations to Scotchman Middle School site will take 9 months; Marshfield extensions and alterations to existing site will take 21 months; Menston alterations to existing site will take 12 months; Miriam Lord alterations to existing site will take 9 months; Moorfield alterations to Lapage Middle School site will take 9 months; Myrtle Park GM extensions and alterations to existing site will take 12 months;

Nessfield extensions and alterations to existing site will take 24 months; Newby extensions and alterations to existing site will take 12 months;

Oakworth GM extensions and alterations to existing site will take 18 months; Oxenhope CE VA extensions and alterations to existing site will take 12 months;

Parkland alterations to existing site will take 9 months; Parkwood alterations to existing site will take 9 months; Poplars Farm extensions and alterations to existing site will take 9 months; Priestthorpe extensions and alterations to existing site will take 18 months; Princeville extensions and alterations to existing site will take 24 months;

Reevy Hill extensions and alterations to existing site will take 24 months; Russell Hall GM extensions and alterations to existing site will take 12 months; Ryecroft extensions and alterations to existing site will take 12 months;

Saltaire alterations to existing site will take 12 months; Sandal alterations to Belmont Middle School site will take 12 months; Sandy Lane extensions and alterations to existing site will take 21 months; Shibden Head extensions and alterations to Hainsworth Moor Middle School site will take 15 months; Shirley Manor extensions and alterations to existing site will take 12 months; Spinkwell new school will take 27 months; Springwood extensions and alterations to existing site will take 21 months; St Andrew's CE VA alterations to existing site will take 9 months; St Augustine's CE new built - Oxford Road site will take 27 months; St Barnabas' CE VA extensions and alterations to existing site will take 21 months; St John's CE GM alterations to Broomwood Middle School site will take 15 months. St Luke's CE extensions to existing site will take 18 months; St Mary's CE VA extensions and alterations to Grange Middle School site will take 24 months; St Matthew's CE extensions to existing site will take 15 months; St Oswald's CE, VA alterations to Great Horton Middle School site will take 21 months; St Paul's CE,VA extensions and alterations to existing site will take 15 months; St Philip's CE new school will take 27 months; St Stephen's CE,VA extensions and alterations to existing site will take 9 months; Stanbury extensions and alterations to existing site will take 18 months; Steeton Junior and Infant extensions and alterations to existing site will take 18 months; Stocks Lane extensions to existing site will take 9 months;

The Church alterations to Leaventhorpe Middle School site will take 9 months ;Thorn Garth new school, 30 months; Thornbury new school, 30 months; Thornton extensions and alterations to Royd Mount Middle School site will take 18 months; Thorpe alterations to existing site, will take 12 months; Tyersal extensions to existing site will take 15 months;

Usher Street alterations to existing site will take 15 months; Utley new school ambulance TC site will take 27 months;

Waverley alterations to existing site will take 9 months; Wellington extensions to existing site will take 15 months; Westbourne extensions to existing site will take 15 months; Whetley alterations to existing site will take 12 months; Wibsey extensions and alterations to existing site will take 21 months; Wilsden extensions to existing site will take 21 months; Windhill CE extensions and alterations to existing site will take 21 months; Woodlands CE extensions to existing site will take 15 months; Woodside alterations to existing site will take 12 months; Worth Valley extensions and alterations to existing site will take 15 months; Worthinghead alterations to existing site will take 9 months; Wycliffe CE,VA alterations to existing site will take 15 months.

SECONDARY SCHOOLS

Beckfoot Grammar extensions and alterations to existing site will take 30 months; Belle Vue Boys extensions and alterations to existing site will take 24 months; Belle Vue Girls extensions and alterations to existing site will take 24 months; Bingley Grammar GM extensions and alterations to existing site will take 30 months; Bowling Community College VA extensions and alterations to existing site will take 30 months; Buttershaw extensions and alterations to existing site will take 30 months; Carlton Bolling College extensions and alterations to existing site will take 30 months;

Challenge School new school will take 30 months; Cote Farm Secondary VA new school will take 33 months; Greenhead Grammar extensions and alterations to existing site will take 30 months; Hanson Secondary GM alterations to existing site will take 18 months; Ilkley Grammar VC extensions and alterations to existing site will take 30 months;

Laisterdyke Secondary GM extensions and alterations to existing site will take 30 months; Nab Wood Grammar extensions and alterations to existing site will take 24 months; Oakbank Grammar GM alterations to existing site will take 18 months; Parkside Secondary extensions and alterations to existing site will take 30 months;

Queensbury extensions and alterations to existing site will take 30 months;

Rhodesway alterations to existing site will take 30 months;

Salt Grammar extensions and alterations to existing site will take 30 months;

The Grange School extensions and alterations to existing site will take 30 months; Thornton Grammar GM extensions and alterations to existing site will take 30 months; Tong extensions and alterations to existing site will take 24 months;

Wyke Manor extensions and alterations to existing site will take 30 months; new Voluntary Aided Muslim School, Feversham College alterations and repairs to St George's will take 24 months.